| Date | Work |
| 22nd February 2006 | Brian Turner came to carry out the pre-covering inspection. All went well. |
| 25th February 2006 | Started disassembly of all the major components. |
| 27th February 2006 | Fitting of control cable guides for elevators and rudder etc. |
| 1st March 2006 | Fitted a couple of new pulleys in the top elevator control cable to keep the exit cable static and stop it rubbing on the elevator woodwork when relaxed. |
| 3rd March 2006 | Finished glueing the rest of the control cable guides. Started looking at a trim lever. |
| 5th March 2006 | Tried one idea for a trim lever, not so good. I will think of something else. |
| 10th March 2006 | Finally have a trim lever I like. Just have to hope the springs are going to the correct tension. |
| 20th March 2006 | Have now finished unbolting everything from the fuselage. Only the undercarriage mounting brackets to remove. I’ll make up the nut plates first. |
| 24th March 2006 | Finished making the nut plates. Removed the undercarriage mounting brackets. |
| 25th March 2006 | Put everything in separate plastic bags. Need to glue the cowling/cockpit ally fittings to the fuse. |
| 4th April 2006 | Glue the fittings for the ally cockpit cover and front cowling. I can now use SS screws to screw the ally to the fuse. |
| 8th April 2006 | Spent a couple of days just sanding everything ready for a final varnish coat. |
| 28th April 2006 | Gave the whole fuse (outside) two more coats of varnish. This was sprayed on with the new spray equipment. Will turn over and do the inside. |
| 30th April 2006 | Sprayed one coat of varnish on the inside before the spray gun blocked up. |
| 2nd May 2006 | Brush varnished the inside. I decided not to paint the inside, just leave the wood clear varnished. |
| 4th May 2006 | Took the undercarriage and tailwheel to be powder coated. Started painting the control columns etc. |
| 6th May 2006 | Started the re-installation of the electrics with a revarnished and finished instrument panel. |
| 7th May 2006 | Continued re-installing the instrument panel. |
| 8th May 2006 | Finished painting the control columns etc. Re-installed the engine control levers. |
| 12th May 2006 | Started re-installing the control columns and rudder/pedals. |
| 15th May 2006 | Fitted some checker plate aluminum to the floor and under the rudder bar and pedals. This will act as a kick plate. |
| 18th May 2006 | Finished fitting the controls, rudder, elevator bell crank, rear fuse fittings. Electrical all complete in fuse. Started fuel system re-installation. |
| 20th May 2006 | Made up some stainless steel straps to hold front fuel header tank. Both fitted in place. |
| 21st May 2006 | Fitted fuel tubing and tap/valve. |
| 22nd May 2006 | Fitted seat belts, rudder cable guides etc. |
| 24th May 2006 | Sanded and prepared tail feathers for covering. Waiting for a thermometer to calibrate iron. Glued in ply gussets around the control horns. Provides something to glue fabric to. |
| 27th May 2006 | Made and fitted radio bracket. Needs some varnish. |
| 29th May 2006 | Started making the firewall. Re-faced the cockpit side of the firewall with 1/16th ply. |
| 30th May 2006 | Re-Drilled all the firewall through points and mounting holes. Bought some stainless steel for the firewall. |
| 3rd June 2006 | Cut and shaped the stainless for the firewall. |
| 5th June 2006 | Coated the horizontal and vertical stab with two coats of poly-brush. |
| 7th June 2006 | Poly-tak’ed the fabric to the horizontal stab both sides. Ironed to shrink. |
| 10th June 2006 | Tried rib stitching for the first time. Completed the horizontal stab stiching. |
| 11th June 2006 | Added the chord wise tapes to the horizontal stab. |
| 14th June 2006 | Completed the vertical stab covering (except LE/TE tapes). Started the rudder, fabric covered one side. |
| 15th June 2006 | Fabriced the second side of the rudder. Poly brushed one coat. |
| 16th June 2006 | Rib stitched the rudder. Poly brushed the tapes (except the L/E and T/E tapes). |
| 18th June 2006 | Glued firewall ply to front of fuse. Now already to cover the fuse. |
| 20th June 2006 | Fabric on both sides of one elevator. |
| 21st June 2006 | Rib stitched one elevator. |
| 22nd June 2006 | Tapes poly brushed to one elevator. Fabric on one side of the other elevator. |
| 23rd June 2006 | Fabric on other side of elevator. |
| 24th June 2006 | Poly brush one coat on elevator. |
| 26th June 2006 | Rib stitched the last elevator. |
| 27th June 2006 | Finished the tail feather covering (apart from edge tapes). |
| 28th June 2006 | Covered both sides of the fuse. |
| 29th July 2006 | Covered bottom of fuse. |
| 30th July 2006 | Covered turtle deck. Poly brush first coat over the whole fuse. |
| 2nd July 2006 | Poly Brushed the side, bottom and end tapes on the fuse. |
| 4th July 2006 | Re-fitted the U/C and engine mount fittings. Will mask when painting. The fitting of the pieces holds the fabric in place when I spray the next two coats of poly brush. |
| 5th July 2006 | Marked out the exit points for the control cables. Will do a temp fit of the tail feathers to confirm exits. |
| 9th July 2006 | Covered the top of the center section. |
| 10th July 2006 | Covered the bottom of the center section. First coat of poly brush. Still needs the tapes. |
| 20th July 2006 | Finally finished all the edge tapes. Glued the control cable fairings to the fuse. Now ready to paint. |
| 25th July 2006 | Bought some clear poly sheeting and made up a temp spray booth. |
| 26th July 2006 | First coat of poly brush on the horizontal stab and fin. Too much! |
| 27th July 2006 | Tried Poly Brush with the rudder and elevators. Much better. |
| 4th August 2006 | Spent a few days spraying poly brush on the tail feathers and centre section. Still first coat. |
| 7th August 2006 | Spent a few more days spraying poly brush on the tail feathers and centre section. This is the second and third coats. |
| 8th August 2006 | Decided the horizontal stab looked rubbish so recovered and resprayed. Much better. Amazing how much quicker things are the second time round! |
| 10th August 2006 | First coat of poly spray applied to tail feathers and center section. |
| 13th August 2006 | Second coat of poly spray applied to center section and fin. |
| 19th August 2006 | Finished the colour coats on the center section and tail feathers. Looks good. A few masking problems with some cheap tape and paper. Will need a little cleaning up. |
| 22nd August 2006 | Cleaned out the workshop. Made up a fuse turning rig and masked up the fuse. Better quality masking paper and tape. |
| 26th August 2006 | Finally finished with the paint on the fuse. A few more bleed throughs but fixable. Obviously didn’t get the correct masking tape. |
| 27th August 2006 | Re-fitted under carriage and tail wheel. |
| 28th August 2006 | Re-fitted all the tail feathers and bracing wires. |
| 29th August 2006 | Re-fitted the center section, strut bracing wires and aileron control wires. |
| 30th August 2006 | Fitted all items to firewall including engine mount. |
| 31st August 2006 | Fitted engine. |
| 1st September 2006 | Re-fitted inlet manifold, exhaust manifold, starter motor etc. |
| 2nd September 2006 | Reconnected all fuel lines, electrics and welded oil/air seperator lines. |
| 4th September 2006 | Made up a carb heat box attached to the exhaust manifold. Fitted hose to the oil/air seperator. |
| 6th September 2006 | Fitted SCAT tube for carb heat and carb to gasloator hose. Started cutting the cockpit covering from aluminium. |
| 8th September 2006 | Re-fitted prop. Finished cutting the aluminium for the cockpit cowling. Needs finishing and fitting. |
| 10th September 2006 | Fitted the aluminium cockpit cowling. Needs some trimming and painting. Will leave until weight and balance is done. I may need to shift the wing. |
| 11th September 2006 | Moved one wing to the work bench. Cleaned it all up and tightened the turnbuckles so that the wing is square. |
| 12th September 2006 | Lock wired all the turn buckles. Applied the first coat of poly brush ready to cover. |
| 13th Septermber 2006 | Covered the first side of the wing. |
| 14th September 2006 | Covered the second side of the wing. |
| 15th September 2006 | Spent the day with Mai rib stiching. Finished the wing. |
| 16th September 2006 | Heat shrunk at 350 degrees all over and applied one coat of poly brush to the bottom of the wing. Covered and poly brushed the aileron. |
| 17th September 2006 | Poly brushed the top of the wing. Turned over when dry and finished all the bottom tapes. |
| 18th September 2006 | Finished the tapes on the top of the wing. Wing ready for paint. |
| 19th September 2006 | Finished taping the aileron. Preped the last wing for covering. |
| 20th September 2006 | Covered the top of the wing. |
| 21st September 2006 | Covered the bottom of the wing. |
| 22nd September 2006 | Covered the starboard aileron, ready for rib stitching. |
| 23rd September 2006 | Rib stitched half the wing. |
| 24th September 2006 | Completed the rib stitching of the wing. |
| 25th September 2006 | Finished 350 degree heat shrinking and first coat of Poly Brush. Poly brushed the tapes on the top of the wing. |
| 26th September 2006 | Poly brushed the tapes on the bottom of the wing. Rib stitched and then Poly Brushed the tapes on the aileron. |
| 27th September 2006 | Completed the wing. Added cable fairings and drain grommets. Both wings now ready for paint. |
| 28th Spetember 2006 | Cleaned up the flying struts. Welded the washer or the rear struts. |
| 30th September 2006 | Fitted the wings again so as to check the flying struts. All worked out well. |
| 1st October 2006 | Finished the flying struts and took the to be powder coated. Took the seat cushions for covering. |
| 2nd October 2006 | Cut and shaped the lexan for the windscreens. |
| 3rd October 2006 | Fitted the windscreens and the cowling mounting brackets. Painted the cockpit covers. |
| 4th October 2006 | Fitted the painted cockpit covers and installed the screens and seats. Poly-brushed one side of the ailerons. |
| 7th October 2006 | Took the fuse to the airport. Nice to have it in the right place! Poly Brushed and poly sprayed the ailerons. |
| 8th October 2006 | Poly brush and one coat of poly spray on one side of one wing. |
| 9th October 2006 | Poly brush and one coat of poly spray on the other side of one wing. First coat of colour on one side. |
| 10th October 2006 | Fitted aileron and finished the other side of the wing with colour. |
| 11th October 2006 | Poly brush and one coat of poly spray on one side of the last wing. |
| 12th October 2006 | Poly brush and one coat of poly spray on the other side of the last wing. |
| 13th October 2006 | Fitted aileron and added the second coat of Poly Spray and two coats of Poly Tone. |
| 14th October 2006 | Turned over wing and added one coat poly spray and two poly tone. |
| 15th October 2006 | Masked up one wing and added the colour highlight. One wing now complete. |
| 16th October 2006 | Masked up the second wing and added the colour highlight. Both wings now complete. |
| 17th October 2006 | Took both wings out to the airport. |
| 18th October 2006 | Fitted both wings, struts and bracing wires. Connected ailerons. All working OK. |
| 19th October 2006 | Made up a tow hook for the hangar. |
| 20th October 2006 | Took the cowl mould to the workshop for checking. Still needs a little work. |
| 21st October 2006 | At the hangar, fiddling……. |
| 22nd October 2006 | Finished the cowl mould. Carried out a radio check. Looks like a little feedback though the PTT cable. |
| 26th – 29th October 2006 | Wings Over Wagga Fly in. |
| 3rd November 2006 | Spent a few days fiddling in the hangar again. Picked up the cowl bowl and measured up (again) for the cowling ally. |
| 13th Novermber 2006 | Spent a few days remaking the cowling bowl and fitting the cowl. All it needs now is a coat of paint. I have also fitted the wing join covers although they need a coat of paint as well. |
| 14th November 2006 | Picked up Darrens prop so as to do some engine tests and slow taxi testing. Mine is being balanced. |
| 15th November 2006 | Fitted the temporary prop and ran the engine again. Felt good but the throttle is a bit spongy when pulled to idle. |
| 17th November 2006 | Finished the cowling air intake and front cooling vents. |
| 18th November 2006 | Fitted the new prop. Much better. Realy looks the part. I will remove the cowling tomorrow for painting. |
| 19th November 2006 | Removed and painted the cowling. |
| 21st November 2006 | One more coat to the cowling. |
| 22nd November 2006 | Carried out the first weight and balance. Came out tail heavy so will need to move the wing back. |
| 23rd – 26th November 2006 | Moved the wing back three inches. Mean new holes for the bracing wires, aileron control cable etc, etc, etc……. Change one thing: change a bundle.. |
| 27th November 2006 | Weight and balance carried out again. This time OK. |
| 28th – 29th November 2006 | Getting ready for the C of A. Had to make up some baffling for the engine. |
| 30th November 2006 | I do belive its finished!!!!!!! |
| 2nd December 2006 | Had the Certificate of Airworthiness issued today. So now we can go and fly!!!! |
| 12th December 2006 | Spent some days taxi-ing and getting the feel of the plane. Still with my old prop. Had some temp issues and increased the baffling around the engine. Feels good….. |
| 17th December 2006 | First Flight…………. |
