Date |
Work |
May 2002 |
Make up parts and material list |
14th June 2002 |
Order William Wynne’s manual |
20th June 2002 |
Order spruce for wing ribs from ASandS. |
July/August 2002 |
Build wing rib jig |
11th Sept 2002 |
Spruce arrives |
15th September 2002 |
Built wing rib No. 1 |
16th September 2002 |
Built wing rib No. 2 |
17th September 2002 |
Built wing rib No. 3 |
20th September 2002 |
Built wing rib No. 4 |
21st September 2002 |
Built wing rib No. 5 |
22nd September 2002 |
Built wing rib No. 6 |
23rd September 2002 |
Built wing rib No. 7 |
24th September 2002 |
Built wing rib No. 8 |
28th September 2002 |
Built wing rib No. 9 & No. 10 |
29th September 2002 |
Built wing rib No. 11 |
30th September 2002 |
Built wing rib No. 12 |
1st October 2002 |
Built wing rib No. 13 |
2nd October 2002 |
Built wing rib No. 14 |
3rd October 2002 |
Built wing rib No. 15 (end rib) |
4th October 2002 |
Built wing rib No. 16 (end rib) |
5th October 2002 |
Built Aileron ends (2 Nos.) |
6th October 2002 |
Built wing rib No. 17 (Aileron rib) |
7th October 2002 |
Built wing rib No. 18 (Aileron rib) |
8th October 2002 |
Built wing rib No. 19 |
9th October 2002 |
Built wing rib No. 20 |
11th October 2002 |
Built wing rib No. 21 |
12th October 2002 |
Built wing rib No. 22 & No. 23 |
13th October 2002 |
Built wing rib No. 24 |
14th October 2002 |
Built wing rib No. 25 |
15th October 2002 |
Built wing rib No. 26 |
16th October 2002 |
Built wing rib No. 27 |
17th October 2002 |
Built wing rib No. 28 |
20th October 2002 |
Built wing rib No. 29 (Butt Rib) |
21st October 2002 |
Built wing rib No. 30 (Butt Rib) |
22nd October 2002 |
Built wing rib No. 31 (Butt Rib) |
23rd October 2002 |
Built wing rib No. 32 (Butt Rib) |
Oct/Nov 2002 |
Design Prop |
29th October 2002 |
Received William Wynne’s Corvair manual. |
14th November 2002 |
Purchase wood for propeller |
16th November 2002 |
Laminate IROKO for prop blank |
20th November 2002 |
Start to Carve prop blank |
25th November 2002 |
Complete first Carving of prop blank |